Nobody's first renovation goes smoothly, but most of what goes wrong isn't bad luck — it's not knowing the order things happen in. Decisions get made late, when they're expensive, instead of early, when they're free.
This is the whole arc, start to finish: seven phases, what each one asks of you, and roughly how long it takes.
| Phase | Typical duration | Your job |
|---|---|---|
| 1. Decide scope | 1–2 weeks | Work out what actually needs to change |
| 2. Set the budget | A few days | Fix a ceiling, reserve 15% |
| 3. Design & selections | 2–4 weeks | Choose and order everything |
| 4. Hire | 2–4 weeks | Bid, check, contract |
| 5. Permits | Days to weeks | Confirm and let the contractor pull them |
| 6. Construction | 3–6 weeks | Be reachable, decide fast, stay out of the way |
| 7. Punch list | 1–2 weeks | Inspect properly, hold final payment |
Total: often three to four months from first thought to finished room, with three to six weeks of actual construction. The planning is longer than the building, and that's correct.
The most common first-timer mistake is compressing phases 1–4 into a weekend and then spending phase 6 making decisions under pressure.
Start with problems, not products. Write down what's wrong with the bathroom you have: no storage, the shower is cramped, the light is bad, it's dated, there's mould in the corner.
Then separate the list:
This ordering matters because the budget will get tight, and when it does you want to cut from the bottom. Without the list you'll cut whatever is least visible, which is usually in the first category.
Then answer the question that dominates the budget: does the plumbing move? Keeping the toilet, sink and shower where they are keeps the project in a predictable band. Moving them means opening the floor and re-routing drains — often the difference between a mid-range and a high-end budget.
Write down the maximum you can spend, then subtract 15% and call it contingency. Plan the project with what's left.
The 15% isn't pessimism. Bathrooms hide their problems behind tile and under floors, and demolition regularly turns up rot, failed subfloor, or wiring that isn't to code. A reserve makes those a phone call instead of a crisis. If you finish without touching it, you've got 15% back.
Our budgeting guide covers where the money goes and what each scope realistically costs. The headline: labour is typically 40–55% of the total. A budget built from material prices will come in low.
This is the phase first-timers skip and later wish they hadn't.
Choose everything: tile (and grout colour), vanity, countertop, sink, faucet, shower valve and matching trim, showerhead, toilet, glass, mirror, lighting, fan, paint, hardware, accessories. Write it into a list with model numbers.
Why now rather than during construction:
Finish every selection before demolition starts. Nearly every avoidable change order traces back to a decision that hadn't been made yet — and a change order is the most expensive way to buy anything, because you have exactly one supplier and no time.
Get three bids on the same written scope. Handing each contractor your own scope of work is what makes their prices comparable; without it, three numbers tell you nothing. See what to include in a scope of work.
For each candidate, check:
On price: the lowest bid is usually low for a reason — a thinner waterproofing spec, lower allowances, or something omitted. Ask what's different rather than assuming a bargain. The middle bid on a detailed scope is often the honest one.
Be wary of a large upfront deposit. Payments should track completed work.
If plumbing, electrical, structure or ventilation changes, you almost certainly need a permit. Cosmetic like-for-like replacement usually doesn't. Rules are local — one call to your building department settles it. Full detail in our permits guide.
The rough-in inspection is worth welcoming rather than enduring: it's a qualified independent person checking the plumbing, wiring and waterproofing inside your walls at the last moment anyone can see them.
Typical order:
Glass is often last because it's templated to the finished tile — which is why it arrives as a late, surprising invoice.
Don't make the final payment on the day it looks finished. Walk the room properly, in good light, with time:
Write the list, agree a date for it to be closed out, and hold a meaningful final payment until it is. Then get the warranty, the permit sign-off, and the model numbers of everything in writing — you'll want them in five years when a cartridge fails.
Basteq turns your bathroom, scope and ZIP code into a step-by-step roadmap and budget, then tells you what to do next — one step at a time.
Plan my remodel — freeConstruction is typically three to six weeks, but the whole project usually runs three to four months from first thought to finished room once you include deciding scope, budgeting, selections, hiring and permits. The planning genuinely takes longer than the building, and compressing it is the most common first-timer mistake.
Write down what's actually wrong with the room, sorted into must-fix, want-to-fix and nice-to-have — before looking at any products. Then decide whether the plumbing moves, because that single choice dominates the budget more than any material selection.
Three, all pricing the same written scope of work. Without a shared scope the numbers aren't comparable, because each contractor is bidding a slightly different project. The lowest bid is usually low for a reason worth asking about, and the middle bid on a detailed scope is often the honest one.
Before, without exception. Selections drive construction — the shower valve body goes in before tile, vanity dimensions set plumbing heights — and lead times on glass or specialty tile can be weeks. Nearly every avoidable change order traces back to a decision that hadn't been made when it was needed.
Usually yes, if you have another working bathroom. If it's your only one, plan seriously: three to six weeks without a bathroom is harder than people expect, and it's a genuine reason to stage the work or arrange to stay elsewhere. Expect fine dust throughout the house regardless of barriers.
After you've walked a proper punch list, not on the day it looks finished. Test taps, drainage, every switch and outlet, the GFCI test button, and the fan's actual suction; check grout and silicone in corners, and look along the tile in raking light. Agree a date to close out the list and hold a meaningful payment until it is.