What to Include in a Bathroom Remodel Scope of Work

Updated September 2026 · 8 min read

Three bids come back at $14,000, $19,000 and $27,000. The natural conclusion is that one contractor is cheap and one is expensive. The likelier explanation is that they bid three different projects, because nobody told them precisely what the project was.

A scope of work is the document that makes bids comparable and change orders rare. It's the highest-value hour you'll spend on the whole remodel, and you can write the first draft yourself.

What a scope of work is for

Three jobs:

  • Makes bids comparable. When every contractor prices the same defined work, price differences mean something.
  • Prevents change orders. Most change orders come from a sentence that meant different things to each party.
  • Settles disputes. When there's disagreement about whether something was included, the scope is the answer — for both of you.

It's not an adversarial document. Good contractors like a clear scope, because it protects them from a client who "assumed" the mirror was included.

The sections

1. Project summary and site conditions

A paragraph: which bathroom, its approximate dimensions, the overall intent, and whether the layout changes. Then the practical facts a bidder needs — where they park, which door they use, whether there's another working bathroom, hours they can work, and whether pets or children are in the house.

2. Demolition and disposal

What comes out, how far it goes, and who takes it away. Debris disposal is a real cost that gets omitted from bids and appears later.

  • Which fixtures and finishes are removed
  • Whether demolition goes to studs and subfloor, or is partial
  • Anything to be salvaged or protected — a door, a window trim, a floor outside the room
  • Dumpster or haul-away, and who supplies it
  • Dust protection: plastic barriers, floor protection along the route, whether negative air is used

3. Rough-in: plumbing, electrical, ventilation

The expensive, invisible part. Be specific:

  • Plumbing: which fixtures are relocated and which stay; supply line replacement; new shower valve body (specify the model — valve and trim must match); shut-offs
  • Electrical: number and location of new circuits, outlets and switches; GFCI protection; fixture locations; dimmers; heated floor circuit if any
  • Ventilation: fan model and CFM rating, and explicitly that it vents to the exterior — not into the attic
  • Framing: blocking for grab bars (worth doing even if you don't install them yet), recessed medicine cabinet, niche, bench

4. Waterproofing

Give this its own section rather than burying it in "tile work". Name the system and require it be installed per manufacturer instructions as a complete system — membrane, corners, seams and drain flange from one manufacturer. State the extent: shower walls to what height, the pan, the curb, the niche, and any area outside the enclosure.

This is the item most likely to be quietly value-engineered by the cheapest bid, and the one whose failure costs the most.

5. Tile and surfaces

  • Each tile by name and size, and where it goes — floor, shower walls, shower floor, accent, wainscot
  • Pattern and orientation. Straight-set, offset, herringbone — labour differs substantially
  • Grout type and colour, and whether it's sealed
  • Trim and edge treatment: bullnose, metal profile, mitred edges
  • Who supplies the tile, and who's responsible if there isn't enough (specify overage — commonly 10–15%)
  • Shower ceiling: tiled or not. Genuinely ambiguous and worth stating.

6. Fixtures and finishes schedule

A table, with model numbers. This is where vagueness costs the most.

ItemSpecifySupplied by
ToiletMake, model, height, rough-in sizeOwner / contractor
VanityMake, model, width, height, finishOwner / contractor
Countertop & sinkMaterial, edge, sink type, hole countOwner / contractor
FaucetMake, model, finish, hole configurationOwner / contractor
Shower valve & trimMake, model — must be matchedOwner / contractor
Showerhead / hand showerMake, model, finishOwner / contractor
GlassType, thickness, hardware finishOwner / contractor
LightingEach fixture, plus colour temp and CRIOwner / contractor
Mirror / medicine cabinetSize, recessed or surfaceOwner / contractor
Exhaust fanMake, model, CFM, sone ratingOwner / contractor
AccessoriesTowel bars, hooks, paper holder, finishOwner / contractor

The "supplied by" column prevents the most common gap of all — everyone assuming the other party is buying the towel bars.

7. Drywall, paint and trim

Moisture-resistant board where required, finish level, paint product and sheen, number of coats, whether the ceiling is painted, and what happens to door and window casing and baseboard. Also state whether the door itself is being replaced or refinished.

8. Exclusions

Write this section. It is the one that prevents arguments.

List what is explicitly not included: work outside the bathroom, repainting the hallway, unknown conditions behind walls, asbestos or lead remediation, upgrading a panel found to be inadequate, replacing fixtures not listed. Naming these doesn't mean they'll happen — it means both parties know they aren't priced.

9. Allowances

If any remain, state exactly what each covers — material only, or material plus installation — and how the difference is settled if you spend over or under. Better still, replace them with real selections. See how to avoid change orders.

10. Schedule

Start date, expected duration, and any known constraints — a holiday, a delivery date, a lead time. Include how inspections are scheduled, since work stops until they happen. A schedule with milestones is more useful than a single end date.

11. Payment and change-order process

  • Payment schedule tied to milestones, not dates — deposit, post-rough-in, post-tile, final on completion
  • How much is held until the punch list is closed
  • That no change order proceeds without written approval
  • How change orders are priced, and what markup applies
  • Warranty on labour, and how manufacturer warranties on fixtures are handled

Be cautious of a large deposit relative to project size. Payments should track work completed.

12. Completion and punch list

What "done" means: everything functioning, silicone finished, surfaces cleaned, debris removed, and a walkthrough producing a written punch list with a date for closing it out.

Scope checklist

  • Project summary, dimensions, and whether the layout changes
  • Demolition extent, dust protection, and who disposes of debris
  • Plumbing, electrical and ventilation rough-in, specified item by item
  • Fan CFM, and explicitly vented to the exterior
  • Blocking for grab bars, niche, bench, recessed cabinet
  • Waterproofing system named, installed as one system, extent stated
  • Every tile named, with pattern, grout, trim and overage
  • Fixture schedule with model numbers and who supplies each
  • Shower valve and trim matched and specified
  • Drywall, paint product and sheen, trim and door
  • An explicit exclusions list
  • Allowances defined, or eliminated
  • Schedule with milestones and inspection allowance
  • Milestone-based payments and a written change-order process
  • Definition of completion and a punch-list process

Build your scope before you collect bids

Basteq turns your bathroom, scope and ZIP code into a structured plan and task list — the raw material for a scope of work that makes bids comparable.

Plan my remodel — free

Frequently asked questions

What is a scope of work in a bathroom remodel?

A written document defining exactly what work is being done, with what materials, by whom, and what is excluded. It's what makes competing bids comparable, and it's the reference point when there's disagreement about whether something was included.

Who writes the scope of work, me or the contractor?

Either, but you should write the first draft. If you hand the same scope to every bidder, their prices become comparable. Contractors will refine it with detail you can't supply, and a good one will welcome the clarity — it protects them from assumptions too.

Why do my bathroom remodel bids vary so much?

Usually because they're pricing different projects. Different allowances, different assumptions about who supplies fixtures, different waterproofing, and different views on whether debris disposal or the shower ceiling was included. A detailed scope given to every bidder is the only way to know whether a price difference is real.

What should the exclusions section say?

Anything explicitly not priced: work outside the bathroom, hallway repainting, unknown conditions behind walls, asbestos or lead remediation, electrical panel upgrades, and any fixture not listed in the schedule. Naming them doesn't make them happen — it makes clear they aren't in the number.

Should the payment schedule be based on dates or milestones?

Milestones — deposit, after rough-in passes inspection, after tile, and a final payment on completion, with an amount held back until the punch list is closed. Payments tied to calendar dates can come due whether or not the corresponding work has happened.

What's the most commonly forgotten item in a scope of work?

Debris disposal, the shower ceiling, tile trim and edge treatment, and who supplies the small accessories. The most costly omission, though, is waterproofing detail — give it its own section, name the system, and state its extent rather than leaving it inside a general "tile work" line.